Statistics for Regulatory Decision Making- Environmental Laboratory Certification
Application Process
Once a complete application is submitted, the DNR has 90 days to inspect the
laboratory. After any problems found during the inspection are fixed, the DNR has 20 days to
approve the laboratory. The DNR can also choose not to inspect the laboratory if it had recently
been inspected or if the application materials are enough to show compliance with state standards.
Application Response Time When Audit Is Waived
Application response time when an audit is waived.
Application Response Time When Audit Is Not Waived
Application response time when an audit is not waived.
Definitions:
Permit Decision
Here, the term "permit decision" refers to the date on which certification
is granted for tests requested with the application.
Application Completed
Here, the term refers to the date by which all the
required materials associated with an application have been received (and they meet program
requiremenmts.
Last Revised: Thursday July 27 2006
|