Wastewater Facility Plan Report Outline

  1. Background Information / Existing Conditions
    1. Need for Proposed Project
    2. Planning Area
    3. Environmental Setting
    4. Demographic and Land Use Information
  2. Design Criteria
    1. Design year
    2. Sewer service area identified
    3. Infiltration/Inflow Analysis
    4. Sewer System Evaluation Survey (SSES)
    5. Projected population, flows, loadings, and toxicity assessment
    6. Possible discharge locations and effluent limitations
  3. Alternatives Analysis
    1. Identification of Alternatives established with consideration of alternative regionalization schemes, sewer service areas, treatment technologies, facility sites, and discharge locations.
    2. Total present worth (Economic) cost analysis
    3. Environmental impacts of alternative
    4. User charge (Fiscal) cost analysis
    5. Recommended alternative
  4. Public Participation
    1. Public hearings and/or informational meetings conducted to highlight user charges, environmental impacts, and any controversial issues
    2. Consideration of public comments
  5. Interagency and Intra-Agency Comments
    1. Conformance with regional plans
    2. Compliance with other federal, state and local regulations
  6. Selection of Cost-Effective Alternative In accordance with s. NR 110.09(1), Wis. Adm. Code, identify the most cost-effective alternative that will result in the minimum total resources costs over the planning period. The total resources costs include monetary costs, environmental and social considerations, and other non-monetary factors.