DNR Plan Review Procedures
For Large Septage Storage Facilities
In accordance with s. NR 113.12 Wisconsin Administrative Code, the use of a septage storage facility
that has a volume capacity greater than 25,000 gallons requires a DNR plan approval to ensure
compliance with ch. NR 110, Wis. Adm.
Code (PDF, exit DNR), plus a WPDES (Wisconsin Pollutant Discharge Elimination System) operating permit. The use
of a smaller septage storage facility requires the submittal of the Department Form 3400-137 prior
to use and may, on a case by case basis, also be subject to DNR plan review and a WPDES permit if
determined necessary to protect public health and the environment.
"Septage" is defined as the wastewater or contents of septic or holding tanks, dosing chambers,
grease interceptors, seepage beds, seepage pits, seepage trenches, privies or portable restrooms.
This guidance addresses the construction plan approval requirements of NR 110. For information
concerning the WPDES permit, the applicable DNR Permit
coordinator should be contacted. The WPDES permit would be processed separately from the
construction plan review, and would be issued after the plan approval.
For a proposed storage facility, construction plans and specifications with the stamp or seal of a
Wisconsin Professional Engineer should be submitted to:
Thomas A. Gilbert, P.E.
Wisconsin DNR
Bureau of Watershed Management
P.O. Box 7921
Madison, WI 53707-7921
The submittal should include 3 sets of the plans and specifications and 2 copies of
the design report or other supplemental information. The content and format of the plans and specifications should generally conform to the requirements of
s. NR 108.04, Wis. Adm. Code. The submittal should be from, or submitted on behalf of, the person,
corporation or other entity that will be the legal owner of the storage facility after it is
constructed.
If the use of an existing tank or structure were proposed, then a Wisconsin Professional Engineer
would need to be retained to inspect and evaluate the structural integrity of the structure proposed
for use. This engineer should then submit plans and information to verify conformance with the
requirements of s. NR 110.26(10). In some instances a tank leakage test may be required. If any
additional new piping, pumps or mixers will be proposed as part of the permanent installation,
design information and plans and specifications for these items should also be included.
Septage storage facilities must comply with the requirements of s. NR 110.26(10) for sludge storage
facilities. If the septage storage structure will be a lagoon, it must also comply with
s. NR 110.24. The plan submittal should include a design report that describes the basis for
design and provides site information. Site maps should be provided demonstrating adequate separation
distances from water supply wells, residential and commercial buildings, bedrock and high groundwater.
Farm outbuildings, such as a barn, would not be considered as a residential or commercial building.
The design report should also describe the expected operations of the proposed storage facility.
For example, describing the types of wastes to be received, septage receiving and unloading
procedures, and ultimate disposal.
The Department also highly recommends that local officials and neighbors be notified of the proposed
storage facility prior to the submittal of plans. Local zoning issues must be dealt with at the
local level.
The submittal must also include the following information describing the environmental impacts of
the proposed facility and its operation.
- Description of existing land use and resource features (e.g. wetlands, lakes, streams,
floodplains, groundwater) that may be affected by the proposed project.
- Impacts on flora and fauna. The potential existence of endangered or threatened resources
should be identified.
- Impacts on prime agricultural land.
- If the proposed site is undisturbed, the potential existence of archaeological and historic
resources should be checked.
- Description of impacts associated with facility operation, including truck traffic, odor
generation and other potential nuisance conditions.
- Description of mitigative measures, if applicable, to be employed to address identified adverse
impacts.
With regard to items 2 and 4, if the area affected by construction is previously disturbed cropland,
a lawn, or some other area where it may be obvious that there are no endangered species or
archaeological resources, then no further information may be needed. Where there is a reasonable
possibility for the occurrence of these resources, then additional information should be sought.
For information on endangered and threatened species, the form entitled
"Wisconsin Natural Heritage Inventory Information Request
Form" should be completed and submitted to the Department's Bureau of Endangered Resources.
For archaeological resource information, contact the DNR Archaeologist:
Mark Dudzik, Archeologist
WDNR Bureau of Facilities and Lands
P.O. Box 7921
Madison, WI 53707-7921
Phone: 608-266-3462
E-Mail: mark.dudzik@dnr.state.wi.us
Information relating to agricultural land impacts should be described but an Agricultural Impact
Statement (AIS) prepared by the Department of Agriculture, Trade and Consumer Protection would not
normally be required. Agricultural Impact Statements are only applicable to projects for public
entities that may acquire property by condemnation as identified under Chapter 32, Wisconsin Statutes.
After it is determined that the proposal complies with applicable rules and will not result in
significant adverse environmental impacts, the Department will issue a news release to the local media.
The news release will describe the proposed facility location and operation, and allow a two-week
time period for receiving public comments. After public comments are evaluated, the Department will
either confirm a decision to approve the proposal, or will request additional information or project
revisions to address issues identified by public comments. The Department will issue a plan approval
to the legal owner of the proposed structure. Construction cannot commence prior to the DNR
issuance of the plan approval.
Last Revised: Monday August 28 2006
|